en Español

May 15, 2007
HSC Helps “Lift” Archer Western to New Heights
 
A new era in the bridge construction business began in 2007 when Archer Western Contractors launched the road-widening project on Interstate 85 South of Atlanta, Ga. Archer Western has constructed bridges throughout the United States including the new bridge and runway at Hartsfield-Jackson International Airport. This new project would take them into the arena of not only building new bridges but raising & repairing them as well.

When Josh Blythe, Project Manager for this job began looking for a suitable cylinder that would accommodate his needs he contacted several Enerpac distributors including Hydraulic Supply Company. Joel Seehafer, Sale Representative for HSC, met with Josh & other Engineers to review their request for quote and learn more about their needs. Within a matter of a few days HSC, along with Ed & Mike Nudd from Enerpac were ready to present a package solution to help Archer Western achieve the monumental task of raising 11 bridges along one of the busiest sections of interstate in Georgia.

The entire package that included 8 pumps & 48 – 100 Ton Cylinders was then sent to Enerpac’s Integrated Solutions division where Engineer’s Pete Crisci & Corey Reyonlds went to work. The complete layout of the system was drawn out per the bridge drawings provided and a large part of system was actually assembled prior to delivery at the jobsite. HSC also worked hand in hand with Enerpac at the job-site assisting with initial set up and installation of all the equipment required. The day of the first ever bridge lift Archer Western attempted was a huge success! The first bridge was lifted 19 inches from its original position, new foundations installed, and all the roadwork completed within 7 days. The Enerpac equipment performed flawlessly as did the massive team from Archer Western. Congratulations to all involved!!
 
Joel Seehafer

 

Close Window